LEVL Coat 104 RAPID — fast epoxy primer for polymer floors
Epoxy primer with accelerated curing under LEVL floors: foot traffic after 6 hours, full strength in about 12 hours at +20 °C.

LEVL Coat 202 W two-component water-based epoxy paint is vapour-permeable and suitable for fresh concrete and for rooms with high humidity and sanitary and hygiene requirements. Priming is done with the same material diluted with water, then at least two coats are applied crosswise with a velour roller. The coating is matt, with Taber abrasion up to 90 mg and adhesion to concrete over 4 MPa; it should be cleaned with alkaline products only. It is used in workshops, warehouses, the food and pharmaceutical industries, schools, kindergartens and healthcare facilities.
| Manufacturer | LEVL (INGRI) — OOO “Ingri”, Saint Petersburg |
|---|---|
| Type | epoxy floors |
| Use | production workshops, retail and public buildings, warehouses and logistics, food and pharmaceutical, wet rooms |
| Base | two-component water-based epoxy paint; no organic solvents or plasticisers |
| Colour | RAL colours; matt surface (gloss no more than 10 %) |
| Packaging | 14 kg (A+B kit in two containers); A : B = 7.3 : 1 (by weight) |
| Application method | thin-layer vapour-permeable coatings indoors with increased abrasion-resistance requirements under high humidity, on fresh concrete and where sanitary and hygiene requirements apply; priming with the same material diluted with water up to 7 %; velour roller, at least 2 coats crosswise; tools are cleaned with water |
| Application temperature | air and substrate +15…+25 °C; air humidity no more than 80 %; substrate visually dry; air circulation is mandatory; concrete at least 25 MPa in compression and 1.5 MPa in tension |
| Curing | walkable: +10 °C 24 h, +20 °C 12 h, +30 °C 8 h; light loads 5 / 3 / 2 days; full loads 8 / 6 / 4 days; drying to degree 3 no more than 3 h at +20 °C; coats over the primer after 8–24 h |
| Key properties | Taber abrasion (CS10/1000 g/1000 rev.; 8 days, 23 °C) no more than 90 mg (DIN 53 109); adhesion to concrete > 4 MPa (failure in the concrete); gloss (FB-2) no more than 10 % (ISO 2813); non-volatile content 74 ± 2 %; mix density 1.6 g/cm³; high vapour permeability; pot life +10 °C 50 min, +20 °C 30 min, +30 °C 15 min |
| Consumption | 150–200 g/m² per coat (at least 2 coats); priming (diluted with water) approx. 150–200 g/m², 2 coats recommended |
| Shelf life | 6 months from the date of manufacture; storage at +5…+25 °C in a dry room |
| Standards | TU 2316-003-94613022-06; works per SP 29.13330.2011, SNiP 3.04.01-87; test methods GOST 28513-90, GOST 25271-93, GOST 28574-90, GOST R 52487-2005, GOST 19007-78, DIN 53 109, ISO 2813 |
Data from the manufacturer’s technical data sheet. The coating system, number of coats and quantity are selected for your project on request.
Epoxy primer with accelerated curing under LEVL floors: foot traffic after 6 hours, full strength in about 12 hours at +20 °C.
Coloured epoxy self-levelling floor for warehouses, workshops and car parks that takes full load after about 12 hours at +20 °C.
Cementitious levelling compound for levelling concrete before laying polymer and cementitious floors; subsequent layers after 2–3 days.
One-component primer-impregnation for concrete and metal before LEVL polyurethane coatings; applied at temperatures from −10 °C.
Film-forming curing compound for concrete and toppings based on an aqueous styrene-acrylic copolymer, without organic solvent.
Self-priming acrylic RAL coating for concrete and metal exposed to precipitation and UV; applied at temperatures from −20 °C.